Time and cost management contract TCM15
The Contract for Use with Complex Projects, First Edition 2013 was launched by the Chartered Institute of Building (CIOB) on 23 April 2013 and thought to be the world’s first BIM-ready contract specifically aimed at the management of time in complex construction and engineering projects. It was suited for works of high value or complexity, major real estate projects and engineering or infrastructure projects. It was developed in response to research revealing that large and complex projects suffered time and cost overruns, and that greater contractual attention should be focused on time and cost management.
In November 2015, the Complex Projects Contract was updated in response to feedback from the industry and renamed the Time and Cost Management Contract (TCM15). The name was changed to reflect the core strengths of the contract.
It is intended for use with the CIOB’s Time and Cost Management Contract suite which includes:
- Document No. 1, Contract Agreement.
- Document No. 2, Contract Conditions.
- Document No. 3, Contract Appendices.
- Document No. 4, Subcontract Agreement.
- Document No. 5, Subcontract Conditions.
- Document No. 6, Subcontract Appendices.
- Document No. 7, Consultancy Appointment.
- Document No. 8, Schedules 8 and 9 for the Appointment of the Time Manager.
- Document No. 9, Schedules 8 and 9 for the Appointment of the Contract dministrator.
- Document No. 10 User Notes.
The contract is intended for major construction or civil engineering projects which require a structured approach to time and cost risk management. It is intended for use by companies, public authorities and private individuals where the construction works carried out by the contractor are based on a design prepared under the direction of the employer, or where the contractor designs some, or all of the works. It is also suitable for construction management and management contracting although in this case, some changes are required.
It requires collaboration between the contractor, subcontractors, design consultants, time manager, cost manager, contract administrator and employer, who continuously appraise risk and take action to overcome and mitigate the consequences of time and cost risks and to bring forward completion dates where practical.
Francis Ho, co-author of the contract, said of the new edition: "It's not a contract that needed a lot of changes. We made some minor clarifications and changes based on user feedback and consolidated some of the specialist roles to make the form seem less daunting ... The biggest news is that the main contract has finally been joined by a professional appointment and subcontract.“
Sarah Rock, formerly an Associate at law firm RPC said, “The suite is targeted at niche projects but within that sphere offers real flexibility in managing time and cost with the aim of avoiding disputes.”
[edit] Related articles on Designing Buildings Wiki
- Chartered Institute of Building
- Complex Projects Contract
- Construction contracts
- Flagship first project for CPC 2013
[edit] External references
- Construction Manager magazine, "CIOB Launches Rebranded Time and Cost Management Contract" on 27 November 2015.
Featured articles and news
Quality Planning for Micro and Small to Medium Sized Enterprises
A CIOB Academy Technical Information sheet.
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.